Weekly Road Construction Update Week of January 28 to February 3

This week’s photo shows concrete placement work occurring at the Gribbling Rd Bridge.

Gribbling Road Bridge Replacement (Bend Area) – Bridge foundation and excavation work will be occurring on Gribbling Road near the Central Oregon Irrigation Canal.

Traffic Information – Gribbling Road is closed to traffic at the Central Oregon Irrigation Canal for bridge replacement work. A designated detour route is in place via U.S. Highway 20, Gosney Road and Ward Road. Access for local traffic will be maintained during construction. Work hours are 7 a.m.-6 p.m., Monday through Friday.

***Note that work hours are subject to change based on weather conditions.***

FOR MORE INFORMATION

Visit: deschutescounty.gov or TripCheck.com

Contact: Deschutes County Road Department at (541) 388-6581

News Release Issued: January 26, 2024